Mineral Resources (Sustainable Development) Act 1990

MINING LICENCE No.

I, (insert name), the Minister/acting as delegate of the Minister, grant to (insert full name of holder) of (insert address of holder) this mining licence. The licence is granted under section 25 of the Act and is effective to/for (insert expiry date or term of years from date of registration).

This licence is subject to the following conditions and to the Schedule of Conditions attached—

    1.     The authority given under this licence applies only within the land indicated on the attached plan and is subject to the depth restrictions, if any, indicated on that plan under section 15(9) or 26(3A) of the Act.

    2.     The licensee must make available a copy of—

        (a)     this licence; and

        (b)     any approved work plan or approved variation to a work plan; and

        (c)     any registered work authority—

at a location in or near the licensed area so that an inspector or any other authorised officer can readily inspect them.

    3.     On receiving a work authority, the licensee must notify an inspector of mines and, if required by that inspector, must arrange an on-site briefing for any people the inspector may nominate.

    4.     The licensee must, from the date of registration of the licence, expend
$ per year on work in the licensed area, unless this requirement is varied, or application of this requirement is suspended for a specified period, in accordance with the Act.

    5.     On discovering an additional mineral resource deposit that may be economically viable to mine, the licensee must report the occurrence immediately in writing to the Department Head giving the estimated size, grade and suitability for mining of the deposit, and an estimate of the value of the deposit at the time of discovery.

    6.     Unless otherwise provided for by Schedule 2 to the Act, the licensee must submit a draft of the work plan for mining within 6 months after the registration of this licence or any longer period that may be approved by the Department Head.

    7.     The licensee must pay rent from the date of registration of the licence.

    8.     The licensee must work in accordance with any approved work plan including any time frames specified in the approved work plan.
Sch. 24